A Plant’s Main Distribution, Cut Over in a 36-Hour Shutdown
New transformer, new switchgear in two electrical rooms, and a new way of feeding the plant. Sheridan built almost all of it while the plant ran, then cut over during a 36-hour turnaround while generators kept product moving.
The challenge
An ingredient manufacturer’s two main electrical rooms each had their own transformer and switchgear. The upgrade would change how the plant is fed: a new transformer and new switchgear in the second room would become the hub, and the first room would be fed from it instead of from its own transformer.
The old equipment could only come out with the power off, and the new switchgear needed floor space that a generator and seven VFD and reactor sets were already using. Even during the shutdown, the plant still had to heat, cycle and ship product.
Build early, cut over fast.
We split the job into pre-shutdown, shutdown and post-shutdown work, each with a task-based timeline. The new transformer, its pad and grounding, the medium-voltage feeds, the cable tray and the new feeders all went in while the plant ran, so the shutdown itself came down to removing, setting and terminating.
During the turnaround, more than 55 Sheridan staff worked across two shifts, alongside low- and high-voltage preventive maintenance and other plant project work. Our teams hooked up multiple generators around the plant so it could keep heating, cycling and shipping product with the main power down.
Two rooms, each with its own transformer and switchgear.
The new transformer feeds 3000 A switchgear in Room 2, and a 1600 A breaker there feeds the new 1600 A switchgear in Room 1.
How it came together
Months of preparation, one short window.
Everything that could be done with the plant running was done first, so the shutdown held only the work that needed the power off.
- PlanningMonths ahead
Plan every task
We reviewed the consulting engineer’s drawings and walked every affected area, then built the materials and task lists and a timeline for pre-shutdown, shutdown and post-shutdown work. ESA plans review was part of our scope, and we brought in partners for rigging, scaffolding, medium-voltage terminations, civil works and Eaton commissioning. Unknowns, like where the VFDs would move to and the scope of the fibre link, were named in the quote with budget allowances.
- Transformer yardPre-shutdown
Set the new transformer
Crews installed ducts and an underground cable trough, formed and poured the transformer pad, extended the existing ground grid and craned the new transformer into place. New 27.6 kV primary cables were run and terminated, then coiled in the source room ready for the cutover.
- FeedersPre-shutdown
Pull the new feeders
A 36-inch cable tray now runs from the transformer yard to Room 2, carrying six parallel runs of 1000 kcmil cable in trefoil, terminated at the transformer secondary. A 24-inch tray through the plant carries four parallel runs of 500 kcmil from Room 2 to Room 1. New feeders for four MCCs were pulled, along with trip and alarm wiring, heater and 120 VAC control power, armoured Ethernet between the rooms and a fibre link to the powerhouse.
- Make roomPre-shutdown
Clear the way
Scaffolds went up in both rooms and the yard, the removal of a KATO generator and the relocation of seven VFD and reactor sets were prepared, and the transformer containment walls came down. Eaton pre-commissioned the new transformer and switchgear before the shutdown started.
- Room 2Shutdown
Cut over the hub
With every energy source locked out, crews removed the old transformer and switchgear, finished removing the generator, relocated the VFDs and reactors and set the new 3000 A switchgear. They terminated the 1000 kcmil transformer feeders, re-fed all four MCCs and landed the 500 kcmil feeders for Room 1 on a 1600 A breaker, then completed trip and alarm, 120 V, 125 Vdc, Ethernet and fibre connections.
- Room 1Shutdown
Re-feed from Room 2
The old transformer and switchgear came out, the new 1600 A switchgear and a 2000 A splice box went in, the VFDs were relocated, and Room 1 was connected to the new system through the 500 kcmil feeders from Room 2.
- CommissioningClose-out
Commission and hand over
Eaton commissioned the transformer and switchgear and the system came back online. Sheridan then removed the scaffolds, labelled the new distribution equipment and submitted as-built drawings.
Keeping product moving with the power off
A plant turnaround doesn’t stop every process. Our teams hooked up multiple temporary generators around the plant so it could keep heating, cycling and shipping product, and used the same window for low- and high-voltage preventive maintenance and other project work.
On site
From the transformer to the last termination.