A Plant’s Main Distribution, Cut Over in a 36-Hour Shutdown

New transformer, new switchgear in two electrical rooms, and a new way of feeding the plant. Sheridan built almost all of it while the plant ran, then cut over during a 36-hour turnaround while generators kept product moving.

36 hrsPlant turnaround window
55+Sheridan staff on site, two shifts
27.6 kVNew transformer primary feeds
3000 ANew main switchgear, plus a 1600 A lineup

The challenge

An ingredient manufacturer’s two main electrical rooms each had their own transformer and switchgear. The upgrade would change how the plant is fed: a new transformer and new switchgear in the second room would become the hub, and the first room would be fed from it instead of from its own transformer.

The old equipment could only come out with the power off, and the new switchgear needed floor space that a generator and seven VFD and reactor sets were already using. Even during the shutdown, the plant still had to heat, cycle and ship product.

Running plantTwo electrical roomsEquipment in the wayShort shutdown window

Build early, cut over fast.

We split the job into pre-shutdown, shutdown and post-shutdown work, each with a task-based timeline. The new transformer, its pad and grounding, the medium-voltage feeds, the cable tray and the new feeders all went in while the plant ran, so the shutdown itself came down to removing, setting and terminating.

During the turnaround, more than 55 Sheridan staff worked across two shifts, alongside low- and high-voltage preventive maintenance and other plant project work. Our teams hooked up multiple generators around the plant so it could keep heating, cycling and shipping product with the main power down.

Pre-shutdown buildTask-based timelineGenerators for the processEaton commissioningMaintenance in the same window
Before
Transformer→Room 1 switchgear
Transformer→Room 2 switchgear

Two rooms, each with its own transformer and switchgear.

After
New transformer27.6 kV primary→New Room 2 switchgear3000 A · 6 × 1000 kcmil
Room 2 switchgear1600 A breaker→New Room 1 switchgear1600 A · 4 × 500 kcmil

The new transformer feeds 3000 A switchgear in Room 2, and a 1600 A breaker there feeds the new 1600 A switchgear in Room 1.

How it came together

Months of preparation, one short window.

Everything that could be done with the plant running was done first, so the shutdown held only the work that needed the power off.

  1. PlanningMonths ahead

    Plan every task

    We reviewed the consulting engineer’s drawings and walked every affected area, then built the materials and task lists and a timeline for pre-shutdown, shutdown and post-shutdown work. ESA plans review was part of our scope, and we brought in partners for rigging, scaffolding, medium-voltage terminations, civil works and Eaton commissioning. Unknowns, like where the VFDs would move to and the scope of the fibre link, were named in the quote with budget allowances.

  2. Transformer yardPre-shutdown

    Set the new transformer

    Crews installed ducts and an underground cable trough, formed and poured the transformer pad, extended the existing ground grid and craned the new transformer into place. New 27.6 kV primary cables were run and terminated, then coiled in the source room ready for the cutover.

  3. FeedersPre-shutdown

    Pull the new feeders

    A 36-inch cable tray now runs from the transformer yard to Room 2, carrying six parallel runs of 1000 kcmil cable in trefoil, terminated at the transformer secondary. A 24-inch tray through the plant carries four parallel runs of 500 kcmil from Room 2 to Room 1. New feeders for four MCCs were pulled, along with trip and alarm wiring, heater and 120 VAC control power, armoured Ethernet between the rooms and a fibre link to the powerhouse.

  4. Make roomPre-shutdown

    Clear the way

    Scaffolds went up in both rooms and the yard, the removal of a KATO generator and the relocation of seven VFD and reactor sets were prepared, and the transformer containment walls came down. Eaton pre-commissioned the new transformer and switchgear before the shutdown started.

  5. Room 2Shutdown

    Cut over the hub

    With every energy source locked out, crews removed the old transformer and switchgear, finished removing the generator, relocated the VFDs and reactors and set the new 3000 A switchgear. They terminated the 1000 kcmil transformer feeders, re-fed all four MCCs and landed the 500 kcmil feeders for Room 1 on a 1600 A breaker, then completed trip and alarm, 120 V, 125 Vdc, Ethernet and fibre connections.

  6. Room 1Shutdown

    Re-feed from Room 2

    The old transformer and switchgear came out, the new 1600 A switchgear and a 2000 A splice box went in, the VFDs were relocated, and Room 1 was connected to the new system through the 500 kcmil feeders from Room 2.

  7. CommissioningClose-out

    Commission and hand over

    Eaton commissioned the transformer and switchgear and the system came back online. Sheridan then removed the scaffolds, labelled the new distribution equipment and submitted as-built drawings.

Keeping product moving with the power off

A plant turnaround doesn’t stop every process. Our teams hooked up multiple temporary generators around the plant so it could keep heating, cycling and shipping product, and used the same window for low- and high-voltage preventive maintenance and other project work.

On site

From the transformer to the last termination.

Electricians in the electrical room during the switchboard 2 replacement
Switchboard 2 replacementCrews working through the night to remove the old and install the new 1600 A switchgear.
Transformer secondary terminals X1 to X3 with parallel feeder cables, phase-taped red, yellow and blue
Transformer secondaryParallel 1000 kcmil feeders, phase-taped and terminated.
Crew setting and dressing cables into the new switchgear lineup, one electrician on a ladder
New switchgearThe new lineup set, with feeders dressed in from above.
Two electricians dressing feeder cables into a switchgear section
TerminationsFeeder cables dressed into a new switchgear section.
Group lockout box with red padlocks and danger tags from every crew member
Lock out, tag outEvery energy source locked and tagged before work starts.
Temporary generator on a trailer outside the plant at night, with an electrician and cables in the foreground
Generators on siteTemporary power kept the process running through the night.
Design-build & shutdown planning27.6 kV primary feedsNew transformer & pad3000 A & 1600 A switchgearGround grid extension6 × 1000 kcmil secondary4 × 500 kcmil inter-room feedersMCC re-feedsVFD & generator relocationEthernet & fibreEaton commissioningTemporary generatorsAs-built drawings