Power Restored in Hours, Not Days
A switchgear fire took a plant fully offline on a holiday long weekend. Sheridan was on site within the hour and had production running again 31 hours after the call, safely.
The emergency
A fire broke out in a plant electrical room. It started at the 1600 A main breaker and compromised the switchgear that fed the facility, and plant power was lost entirely.
The failure struck on a Sunday during a holiday long weekend, when every hour offline carried real production cost.
Back in production in 31 hours.
Sheridan’s on-call electrician was on site within the hour to assess the damage and make the area safe. As the scale of the failure became clear, the team brought in additional electricians from out of town to work the long weekend.
With the main breaker unusable, the team deployed a 2 MW generator to temporarily feed 600 V / 1600 A into the gear, re-working the buswork downstream to safely accept the temporary feed. Power was restored and the plant was back in production the next afternoon.
Response timeline
Sunday morning to Monday afternoon.
Thirty-one hours from the emergency call to a plant back in full production.
- Sun 9 am0 hrs
Emergency call
The call came in during the holiday long weekend: fire in the electrical room, and no power to the plant.
- Within the hour< 1 hr
Assess and isolate
Sheridan’s on-call electrician was on site to assess the damage, isolate the failure and make the area safe.
- SundaySame day
Crew scaled up
Additional electricians were mobilized from out of town to work through the long weekend, and a 2 MW generator was sourced.
- Mon 8 am+23 hrs
Prepare the gear
With the generator on site, the gear was safely prepared for the temporary feed, including re-working the buswork downstream of the failed main breaker.
- Mon 3 pm+30 hrs
Plant power restored
Plant power was restored on the temporary feed.
- Mon 4 pm+31 hrs
Back in production
The plant was fully back in production, with safety kept at the forefront throughout.
- Next weekProve it out
Permanent breaker installed
The temporary feed was monitored through the following week to prove its reliability, then a permanent breaker was installed.
Fire damage & temporary feed
The failed main breaker, and the temporary feed that took over.


On site
A 2 MW generator, on site within 23 hours of the call.


Fast, without shortcuts
Getting the plant running was the first job; keeping it running was the second. Rather than rush the permanent repair, the temporary feed was monitored through the following week to prove its reliability before a permanent breaker was installed.
Sheridan’s team provided professional solutions in our time of need. This repair turnaround was completed quickly, with a high-level sense of urgency, all while keeping safety at the forefront.
Maintenance Manager, global ingredient manufacturer