Contact us
Home/Electrical Contracting/Case Study: Emergency Switchgear Fire Restoration
Plant switchgear lineup with the fire-damaged main breaker section at left and temporary feed cables entering the gear at right
Case studyIngredient ManufacturingEmergency ServiceCritical Power

Power Restored in Hours, Not Days

A switchgear fire took a plant fully offline on a holiday long weekend. Sheridan was on site within the hour and had production running again 31 hours after the call, safely.

< 1 hrOn-site response
~31 hrsCall to full production
2 MWTemporary power source
1600 A600 V service restored

The emergency

A fire broke out in a plant electrical room. It started at the 1600 A main breaker and compromised the switchgear that fed the facility, and plant power was lost entirely.

The failure struck on a Sunday during a holiday long weekend, when every hour offline carried real production cost.

Total loss of plant powerMain breaker destroyedHoliday long weekend

Back in production in 31 hours.

Sheridan’s on-call electrician was on site within the hour to assess the damage and make the area safe. As the scale of the failure became clear, the team brought in additional electricians from out of town to work the long weekend.

With the main breaker unusable, the team deployed a 2 MW generator to temporarily feed 600 V / 1600 A into the gear, re-working the buswork downstream to safely accept the temporary feed. Power was restored and the plant was back in production the next afternoon.

On-call electricianCrew scaled over the weekend2 MW temporary feedBuswork re-worked

Response timeline

Sunday morning to Monday afternoon.

Thirty-one hours from the emergency call to a plant back in full production.

  1. Sun 9 am0 hrs

    Emergency call

    The call came in during the holiday long weekend: fire in the electrical room, and no power to the plant.

  2. Within the hour< 1 hr

    Assess and isolate

    Sheridan’s on-call electrician was on site to assess the damage, isolate the failure and make the area safe.

  3. SundaySame day

    Crew scaled up

    Additional electricians were mobilized from out of town to work through the long weekend, and a 2 MW generator was sourced.

  4. Mon 8 am+23 hrs

    Prepare the gear

    With the generator on site, the gear was safely prepared for the temporary feed, including re-working the buswork downstream of the failed main breaker.

  5. Mon 3 pm+30 hrs

    Plant power restored

    Plant power was restored on the temporary feed.

  6. Mon 4 pm+31 hrs

    Back in production

    The plant was fully back in production, with safety kept at the forefront throughout.

  7. Next weekProve it out

    Permanent breaker installed

    The temporary feed was monitored through the following week to prove its reliability, then a permanent breaker was installed.

Fire damage & temporary feed

The failed main breaker, and the temporary feed that took over.

Fire damageFire-damaged switchgear section with melted labels and soot around the failed main breaker
Fire damage at the failed 1600 A main breaker.
Temporary feedRows of temporary power cables run along a rack on an elevated walkway, with colour-coded connectors
The temporary power feed, installed and energized within hours.

On site

A 2 MW generator, on site within 23 hours of the call.

Trailer-mounted 2 MW generator beside the plant with temporary power cables coiled in the foreground
The 2 MW generatorTemporary power to feed 600 V / 1600 A into the plant’s gear.
Temporary power cables laid out in the plant yard beside service vehicles
Cables staged in the yardTemporary feed cables laid out before installation, with the service vehicles on site.

Fast, without shortcuts

Getting the plant running was the first job; keeping it running was the second. Rather than rush the permanent repair, the temporary feed was monitored through the following week to prove its reliability before a permanent breaker was installed.

Sheridan’s team provided professional solutions in our time of need. This repair turnaround was completed quickly, with a high-level sense of urgency, all while keeping safety at the forefront.

Maintenance Manager, global ingredient manufacturer
On-call electricianMake-safe & isolationOut-of-town crew mobilization2 MW generator600 V / 1600 A temporary feedBuswork re-workReliability monitoringPermanent breaker installation

Power down right now?

Call 1-800-517-8512, 24/7. Our on-call journeyman electricians arrive with testing instruments and spare parts.