Critical Substation Failure
Rapid response done right. When a leading pharmaceutical company suffered a catastrophic power failure, Sheridan Electric was trusted to respond with urgency and expertise to safely restore power.
The challenge
On the morning of August 14th, a large GTA pharmaceutical customer completely lost power to its facility. The bus duct connecting the main transformer to the 3000 A main switchboard had failed catastrophically.
The company develops and manufactures affordable prescription medications at its GTA production facility. A prolonged power failure would mean extremely steep production and business losses.
Power back the same day. Permanent power in twelve.
Our service team made the site safe and had the plant running on a 1750 kW emergency generator by that evening. Then the real work began: testing confirmed the transformer was damaged, so we sourced a replacement with our partners, helped design a new 3000 A cable bus system, ran a full site coordination study, and worked multiple shifts to install it.
Twelve days after the failure, the new system was energized and the generator removed.
Twelve days
From blackout to permanent power.
Each day on the generator burned 5,400 litres of fuel, so things needed to move quickly.
- Aug 14Morning
Make it safe
The service team evaluated the situation, made it safe, and started preparing the switchboard for back-up power by disconnecting the damaged incoming bus duct. Meanwhile, work began to source a 1750 kW, 600/347 V emergency generator and arrange fuel delivery.
- Within 3 hoursAug 14
Generator on site
The generator arrived, and the team worked through the evening to restore power to the plant.
- DiagnosisFollowing days
Test the substation, design the replacement
With power restored, attention shifted to the damaged bus duct, switchboard and substation. We arranged oil and gas testing to check the substation’s health, while the engineering team helped design a new 3000 A cable bus system to replace the damaged duct.
- Test resultsReplacement needed
Source a new transformer
The results confirmed the worst fear: the transformer had suffered a critical secondary bus-duct short and needed immediate replacement. With help from our partners, we sourced a new in-stock 44 kV transformer.
- ESA approvalExpedited
Swap the transformer, check the protection
Once the expedited ESA plans approval was complete, the old transformer came out and the new one went in. Its impedance was lower than the original’s, so we conducted a full site coordination study to ensure the correct breaker settings were in place.
- Multiple shiftsInstall & inspect
Build the new cable bus
Field teams worked in multiple shifts to install the new secondary cable bus system as fast as possible. As soon as it was complete and inspected by ESA, we coordinated with Alectra Utilities to restore power and remove the generator.
- Aug 26Sunday, 1:15 pm
Energized
Twelve days after the failure, the new system was energized and generator power removed.
Before & after
The failed bus duct, and its replacement.


On site
What the crews found, and what they built.


Why a coordination study
The replacement transformer had a lower impedance than the original. A transformer change like that affects how the plant’s protective devices need to be set, so a full site coordination study confirmed the correct breaker settings before the new system was energized.
Throughout this critical emergency, Sheridan Electric understood the sense of urgency and was completely dedicated and focused on restoring power quickly and safely.
Customer, GTA pharmaceutical manufacturer
To accomplish everything in such a short time wouldn’t have been possible without a complete team effort and a dedication to our purpose: world-class care and total support, 24/7. In a perfect world, breakdowns wouldn’t happen. Until then, we remain committed to being at our strongest when you need us most.
Services used
Power down right now?
Call 1-800-517-8512, 24/7. Our on-call journeyman electricians arrive with testing instruments and spare parts.