CI Flexographic Press Retrofit
Six obsolete DC drives, an unsupported controller and an SLC PLC replaced inside the existing cabinets and consoles — on an 85-day schedule with the press back in production on the planned date.
The challenge
A central-impression flexographic press at a flexible packaging plant was running on six legacy DC drives, a proprietary drive controller and an SLC PLC. Spares were gone, support was gone, and every fault was a longer outage than the last.
The press had to keep its mechanical layout, its cabinets and its three operator consoles. The retrofit had to fit what was there, and the plant needed a date it could plan production around.
The solution
Sheridan Automation engineered the retrofit, produced the drawing set, installed the drives and wiring, programmed the drives and HMI offline while installation ran in parallel, and commissioned the press — with a drives partner supplying the drive and PLC package.
Six regenerative digital DC drives on Ethernet replaced the originals: unwind, rewind, chill roll and main drive. The SLC migrated to CompactLogix. The three consoles were refitted with 10″ PanelView Plus screens and 98 new pushbuttons, lights and selectors on stainless retrofit plates.
Scope of work
Drives, controls, consoles and commissioning — one team.
Engineering & drawings
Five days of engineering, then a full AutoCAD drawing set taken through two rounds of review and approval with the plant before a wire was pulled.
Drive replacement
Six legacy DC drives replaced with regenerative digital drives on Ethernet — unwind, rewind, chill roll and main — in the existing drive cabinets.
PLC migration
Proprietary drive controller and SLC PLC migrated to CompactLogix, with the press logic rebuilt and verified offline over the 45-day installation window.
Operator consoles
Three consoles refitted with 10″ PanelView Plus screens; 98 pushbuttons, E-stops, lights and selectors replaced on new stainless retrofit plates.
Load cells & tension
Existing load cells and amplifiers found unserviceable; new customer-supplied load cells installed, configured and calibrated.
Commissioning & extras
Ten days of commissioning and testing. Impression counter and per-deck auto/manual control added to the main HMI at no charge; a deck-out fault traced through the PLC interlocks to failed control relays.
On the floor
What it looks like.
Managed by the new system
Capabilities used