Contact us
Home/Electrical Contracting/Case Study: Automotive Plant Expansion
Electricians on scaffolding running aluminum cable bus from new transformers in a fenced yard beside the plant
Case studyAutomotiveLarge ProjectCritical PowerValue Engineering

An Automotive Plant Expansion: New Power for a 3000-Ton Press

Complete electrical work for two building additions, as electrical contractor to the design-builder. Sheridan relocated the plant’s high-voltage equipment, installed two new transformers, and engineered an underground feeder route to a new 3000-ton press.

4 + 5 MVANew high-voltage transformers
6000 ALargest new switchboard
1600 AFeeder to the 3000-ton press
14Ducts under the transformer yard

The challenge

An automotive parts manufacturer was adding two buildings to its plant, including a new 3000-ton press. The existing high-voltage switchgear and distribution equipment had to be relocated, two new high-voltage transformers needed secondary feeds, and the press needed power by a fixed date.

The design ran the feeders to the press and three new panels overhead, in copper cable and tray, through buildings that were still going up. The original drawings also had a scaling error, and the electrical room layout had been flipped, which made every feeder longer than drawn.

Two building additionsHV equipment relocationBuildings under constructionFixed press power date

A shorter route, engineered by Sheridan.

We recalculated every feeder length for the scaling error and the flipped room before pricing, and offered value-engineering options, several of which were built into the base bid: aluminum cable bus for the transformer secondaries, copper feeder-bus to the welding and robot bus ducts, and aluminum feeders to the new panels.

The biggest change took the press feeders underground. Instead of overhead copper, Sheridan designed aluminum feeders in a duct bank running straight from the new electrical room, under the new transformer yard, to the press and the panels. The route was much shorter and could go in before the second building’s structure was finished. After engineering review, the change went ahead with a net credit back to the owner and no impact on the schedule.

Value engineeringSheridan-designed feedersUnderground duct bankAluminum cable busNo schedule impact

How it came together

From the transformer yard to the press pit.

Sheridan carried the complete electrical scope for both additions, from the high-voltage equipment to the lighting and fire alarm.

  1. EstimatingBefore award

    Price what will actually be built

    Feeder lengths were recalculated for a scaling error in the original drawings and the flipped electrical room, and value-engineering options were offered up front, several of which the design-builder had us include in the base bid.

  2. RelocationExisting HV gear

    Move the existing equipment

    We relocated the plant’s existing high-voltage equipment to the new transformer yard and its distribution equipment to the new electrical room, then removed a temporary high-voltage feeder from an earlier phase and remediated its splice in the manhole.

  3. Transformers4 + 5 MVA

    Set and feed two transformers

    A 4 MVA and a 5 MVA transformer were craned into the yard. Crews ran and terminated the high-voltage cable from the switchgear to both transformers and installed aluminum cable bus for the secondaries into the building. Substation and perimeter grounding were tied into the plant’s existing ground loop.

  4. Duct bank14 × 4-inch

    Take the feeders underground

    A 14-duct bank, seven wide and two high, leaves the electrical room under the transformer yard and splits outside the building to the press and the panels. The 1600 A press feeder runs in eight parallel runs of 600 kcmil aluminum. As the design developed, we added a spare duct to the press pit, followed a longer requested route, upgraded conductors after engineering review, and switched to surface EMT when the press pit panel turned out to be on a mezzanine.

  5. DistributionUp to 6000 A

    Switchboards, bus and panels

    New switchboards up to 6000 A, copper feeder-bus to the welding and robot plug-in bus ducts (reusing salvaged feeder bus from the existing electrical room), new distribution and branch panels per the single-line diagrams, and connections to the new mechanical equipment.

  6. Life safetyBoth additions

    Lighting and fire alarm

    New lighting throughout, and new fire alarm devices tied into the plant’s existing data loop with signal circuits back to the control panel. Added scope in the existing electrical room brought in new pull stations, horn/strobes and sprinkler flow and tamper switches, verified and tested with the inspector.

Value engineering that went in the ground

We designed the underground feeders ourselves, at no charge for the engineering. Running them straight under the transformer yard was shorter than routing overhead through two new buildings, could be built before the second structure was finished, and came back to the owner as a net credit with no impact on the schedule.

On site

From the crane hook to the last termination.

Crew rigging a new high-voltage transformer off a flatbed while a crane lifts it into the transformer yard
Transformer liftOne of the two new high-voltage transformers, craned into the yard.
Electrician in an excavation beside a bank of grey PVC ducts for the underground feeders
Underground duct bankDucts for the aluminum feeders, run under the transformer yard.
Aluminum cable bus rising from a new 27,600 V transformer and running into the building
Cable bus to the buildingTransformer secondaries run in aluminum cable bus into the new electrical room.
Transformer secondary enclosure with parallel conductors phase-taped and terminated
Transformer secondaryParallel secondary conductors, phase-taped and terminated.
New distribution section with feeder cables terminated on the A, B and neutral bus
Distribution terminationsFeeders landed on the new distribution equipment.
New branch panelboard with feeder cables dressed down the right side
Branch panelsNew distribution and branch panels, per the single-line diagrams.
Electricians on scaffolding running aluminum cable bus from new transformers in a fenced yard beside the plant
Transformer yardCrews running the aluminum cable bus from the new transformers.
Aluminum cable bus run seen from the scaffold, with the building additions under construction behind
Cable bus runAluminum cable bus from the yard, with the building additions going up behind.
Cable bus curving out of the transformer secondary enclosure
Out of the transformerCable bus leaving the transformer secondary enclosure.
Aluminum cable bus rising from a new 27,600 V transformer and running into the building
Cable bus to the buildingTransformer secondaries run in aluminum cable bus into the new electrical room.
Electrician on a lift below the cable bus where it enters the new electrical room
Into the electrical roomThe cable bus entering the new electrical room.
Crew rigging a new high-voltage transformer off a flatbed while a crane lifts it into the transformer yard
Transformer liftOne of the two new high-voltage transformers, craned into the yard.
Electrician in an excavation beside a bank of grey PVC ducts for the underground feeders
Underground duct bankDucts for the aluminum feeders, run under the transformer yard.
Underground ducts sweeping into the building foundation wall
Into the buildingUnderground ducts sweeping into the foundation wall.
Transformer secondary enclosure with parallel conductors phase-taped and terminated
Transformer secondaryParallel secondary conductors, phase-taped and terminated.
New distribution section with feeder cables terminated on the A, B and neutral bus
Distribution terminationsFeeders landed on the new distribution equipment.
Switchgear section with feeder cables terminated on phases A, B and C
Feeder terminationsFeeders terminated phase by phase in the new switchgear.
Feeder lugs landed on the switchgear bus, phase-coloured blue, black and red
Lugs and busFeeder lugs landed and torqued on the switchgear bus.
New branch panelboard with feeder cables dressed down the right side
Branch panelsNew distribution and branch panels, per the single-line diagrams.
Electrical contractor to design-builderHV equipment relocation4 MVA & 5 MVA transformersAluminum cable busSwitchboards up to 6000 A1600 A press feederUnderground duct bankCopper feeder-bus to robot & welding bus ductSubstation groundingLighting & fire alarmValue engineering

Adding a building or a big press?

Send us the drawings. We’ll check them, price what will actually be built, and look for a better way to build it.