An Automotive Plant Expansion: New Power for a 3000-Ton Press
Complete electrical work for two building additions, as electrical contractor to the design-builder. Sheridan relocated the plant’s high-voltage equipment, installed two new transformers, and engineered an underground feeder route to a new 3000-ton press.
The challenge
An automotive parts manufacturer was adding two buildings to its plant, including a new 3000-ton press. The existing high-voltage switchgear and distribution equipment had to be relocated, two new high-voltage transformers needed secondary feeds, and the press needed power by a fixed date.
The design ran the feeders to the press and three new panels overhead, in copper cable and tray, through buildings that were still going up. The original drawings also had a scaling error, and the electrical room layout had been flipped, which made every feeder longer than drawn.
A shorter route, engineered by Sheridan.
We recalculated every feeder length for the scaling error and the flipped room before pricing, and offered value-engineering options, several of which were built into the base bid: aluminum cable bus for the transformer secondaries, copper feeder-bus to the welding and robot bus ducts, and aluminum feeders to the new panels.
The biggest change took the press feeders underground. Instead of overhead copper, Sheridan designed aluminum feeders in a duct bank running straight from the new electrical room, under the new transformer yard, to the press and the panels. The route was much shorter and could go in before the second building’s structure was finished. After engineering review, the change went ahead with a net credit back to the owner and no impact on the schedule.
How it came together
From the transformer yard to the press pit.
Sheridan carried the complete electrical scope for both additions, from the high-voltage equipment to the lighting and fire alarm.
- EstimatingBefore award
Price what will actually be built
Feeder lengths were recalculated for a scaling error in the original drawings and the flipped electrical room, and value-engineering options were offered up front, several of which the design-builder had us include in the base bid.
- RelocationExisting HV gear
Move the existing equipment
We relocated the plant’s existing high-voltage equipment to the new transformer yard and its distribution equipment to the new electrical room, then removed a temporary high-voltage feeder from an earlier phase and remediated its splice in the manhole.
- Transformers4 + 5 MVA
Set and feed two transformers
A 4 MVA and a 5 MVA transformer were craned into the yard. Crews ran and terminated the high-voltage cable from the switchgear to both transformers and installed aluminum cable bus for the secondaries into the building. Substation and perimeter grounding were tied into the plant’s existing ground loop.
- Duct bank14 × 4-inch
Take the feeders underground
A 14-duct bank, seven wide and two high, leaves the electrical room under the transformer yard and splits outside the building to the press and the panels. The 1600 A press feeder runs in eight parallel runs of 600 kcmil aluminum. As the design developed, we added a spare duct to the press pit, followed a longer requested route, upgraded conductors after engineering review, and switched to surface EMT when the press pit panel turned out to be on a mezzanine.
- DistributionUp to 6000 A
Switchboards, bus and panels
New switchboards up to 6000 A, copper feeder-bus to the welding and robot plug-in bus ducts (reusing salvaged feeder bus from the existing electrical room), new distribution and branch panels per the single-line diagrams, and connections to the new mechanical equipment.
- Life safetyBoth additions
Lighting and fire alarm
New lighting throughout, and new fire alarm devices tied into the plant’s existing data loop with signal circuits back to the control panel. Added scope in the existing electrical room brought in new pull stations, horn/strobes and sprinkler flow and tamper switches, verified and tested with the inspector.
Value engineering that went in the ground
We designed the underground feeders ourselves, at no charge for the engineering. Running them straight under the transformer yard was shorter than routing overhead through two new buildings, could be built before the second structure was finished, and came back to the owner as a net credit with no impact on the schedule.
On site
From the crane hook to the last termination.