A 350,000 sq. ft. Bakery, Wired from the Ground Up
A converted building, months of delayed approvals and an end date that didn’t move. Sheridan delivered the electrical contracting and control wiring for a new automated bakery in the GTA, to food-grade installation standards, on time and on budget.
The challenge
A major bakery contracted Sheridan Electric to provide electrical contracting and control wiring for a new 350,000 sq. ft. automated bread and rolls plant in the GTA.
The building was a converted structure with concrete ceilings, which made traditional power distribution methods more costly than normal. Engineering approvals delayed the project by several months, but the end date stayed fixed. And numerous equipment manufacturers were involved, each with its own power and control wiring needs.
On time, on budget.
Instead of fighting the ceilings, we went under the floor: the concrete slab was removed for trenching and underground conduit, saving both time and money. The selection of the motor control centres and the design of the main power distribution were Sheridan’s responsibility.
To absorb the approval delays, our foreman and scheduling team scaled the labour force as needed to meet or exceed deadlines, running two shifts and working weekends as necessary.
Throughout, the installation followed clean design standards and food-grade installation methods.
How it came together
From an empty floor to full operation.
Sheridan was involved from the very start of the project through to production support.
- Below the slabFrom the start
Take the power underground
With the concrete floor removed, crews trenched and installed all the underground conduit that would form the plant’s critical power distribution, including underground feeds to the wet areas and production sub-services. With the floor already open, this saved the cost of running that conduit on the roof.
- Stakeouts200+ locations
Place every stub-up precisely
With more than 200 stub-up locations for equipment wiring, pipe placement had to be exact. Locate services and detailed engineered drawings put the underground conduit where future machines would stand.
- DistributionHV to 6000 A
From the substation to every line
An HV substation and HV distribution feed a 6000 A and a 3000 A low-voltage switchboard, with multiple sub load centres and power for the equipment control panels. Motor control centres went into key sections of the plant, some more than 800 ft from the source. Sheridan selected the MCC cabinets and designed the main power distribution.
- BatchingDry, wet & silos
Wire the batching system
The large, complicated batching system linked dry rooms, wet rooms and outdoor silos for sugar, flour and more through four Zeppelin batching control panels. Devices were terminated at the top and bottom of every silo for level detection, valves and motors, with weigh scale cables run back to the main control panel. Cable tray and conduit were planned carefully to manage the volume of power and control wiring.
- OEM equipmentMilestones
Power and control for every OEM
Motor, control and OEM wiring for the multi-level Rexfab conveyor system, AFA machines, ovens, AMF dough formers, packaging and cooling spirals. Through continuous planning with the client’s engineers and OEM representatives, we met the set milestones, ran I/O checks with each OEM, and supported start-up, programming and commissioning.
- HandoverToward full operation
PLC and shift coverage
After substantial completion, Sheridan provided regular and after-hours coverage to support the production and maintenance departments as the plant moved toward full operation.
Food safety, built in
In a bakery, the electrical installation is part of the food safety program and has to meet the same standard as the rest of the plant. Sheridan followed clean design standards and food-grade installation methods throughout, and installed food-grade lighting in the plant. Our field teams are trained for regulated environments, including GMP and food safety.
On site
From below the slab to the production floor.




























On schedule, and right the first time
Engineering approvals took several months longer than planned, and the finish date didn’t move. Careful coordination with the mechanical and other sub-trades kept the schedule on track, and with a large crew on site, potential backlogs were identified early to eliminate wasted labour hours. A point of pride for the team: almost no start-up or device termination issues.