Home/Electrical Contracting/Case Study: Automated Bakery Build-Out
Panorama of the bakery floor with the concrete slab removed and underground conduit being laid in trenches
Case studyFood & BeverageLarge ProjectBakeryFood Safety

A 350,000 sq. ft. Bakery, Wired from the Ground Up

A converted building, months of delayed approvals and an end date that didn’t move. Sheridan delivered the electrical contracting and control wiring for a new automated bakery in the GTA, to food-grade installation standards, on time and on budget.

350,000Sq. ft. automated bakery
200+Equipment stub-up locations
800+ ftFurthest MCC from the source
6000 AMain LV switchboard

The challenge

A major bakery contracted Sheridan Electric to provide electrical contracting and control wiring for a new 350,000 sq. ft. automated bread and rolls plant in the GTA.

The building was a converted structure with concrete ceilings, which made traditional power distribution methods more costly than normal. Engineering approvals delayed the project by several months, but the end date stayed fixed. And numerous equipment manufacturers were involved, each with its own power and control wiring needs.

Concrete ceilingsMonths of approval delaysFixed end dateMany OEMs

On time, on budget.

Instead of fighting the ceilings, we went under the floor: the concrete slab was removed for trenching and underground conduit, saving both time and money. The selection of the motor control centres and the design of the main power distribution were Sheridan’s responsibility.

To absorb the approval delays, our foreman and scheduling team scaled the labour force as needed to meet or exceed deadlines, running two shifts and working weekends as necessary.

Throughout, the installation followed clean design standards and food-grade installation methods.

Underground distributionMCC selection & designTwo shifts & weekendsFood-grade install methodsOEM commissioning support

How it came together

From an empty floor to full operation.

Sheridan was involved from the very start of the project through to production support.

  1. Below the slabFrom the start

    Take the power underground

    With the concrete floor removed, crews trenched and installed all the underground conduit that would form the plant’s critical power distribution, including underground feeds to the wet areas and production sub-services. With the floor already open, this saved the cost of running that conduit on the roof.

  2. Stakeouts200+ locations

    Place every stub-up precisely

    With more than 200 stub-up locations for equipment wiring, pipe placement had to be exact. Locate services and detailed engineered drawings put the underground conduit where future machines would stand.

  3. DistributionHV to 6000 A

    From the substation to every line

    An HV substation and HV distribution feed a 6000 A and a 3000 A low-voltage switchboard, with multiple sub load centres and power for the equipment control panels. Motor control centres went into key sections of the plant, some more than 800 ft from the source. Sheridan selected the MCC cabinets and designed the main power distribution.

  4. BatchingDry, wet & silos

    Wire the batching system

    The large, complicated batching system linked dry rooms, wet rooms and outdoor silos for sugar, flour and more through four Zeppelin batching control panels. Devices were terminated at the top and bottom of every silo for level detection, valves and motors, with weigh scale cables run back to the main control panel. Cable tray and conduit were planned carefully to manage the volume of power and control wiring.

  5. OEM equipmentMilestones

    Power and control for every OEM

    Motor, control and OEM wiring for the multi-level Rexfab conveyor system, AFA machines, ovens, AMF dough formers, packaging and cooling spirals. Through continuous planning with the client’s engineers and OEM representatives, we met the set milestones, ran I/O checks with each OEM, and supported start-up, programming and commissioning.

  6. HandoverToward full operation

    PLC and shift coverage

    After substantial completion, Sheridan provided regular and after-hours coverage to support the production and maintenance departments as the plant moved toward full operation.

Food safety, built in

In a bakery, the electrical installation is part of the food safety program and has to meet the same standard as the rest of the plant. Sheridan followed clean design standards and food-grade installation methods throughout, and installed food-grade lighting in the plant. Our field teams are trained for regulated environments, including GMP and food safety.

On site

From below the slab to the production floor.

Tall electrical room with motor control centres and control cabinets, conduit running down the white walls
Electrical roomMCCs and control cabinets, with conduit run down from above.
Electrician landing field wiring on PLC input and output modules inside a large control cabinet
Control wiringTerminations and I/O landed in a process control panel.
Electrician on a boom lift working at the top of a row of outdoor ingredient silos with conduit running down each silo
Outdoor silosLevel detection, valves and motors terminated at the top and bottom of each silo.
Tall stainless cooling spirals with access stairs and platforms, and an infeed conveyor in the foreground
Cooling spiralsAll devices and main power feeds wired to the cooling spirals, with I/O checks and start-up support for the OEM.
Plant floor with overhead conveyors installed, process equipment arriving and lifts in use
Production floorThe Rexfab conveyor system for product transfer, with motors wired on aluminum rigid drops from the ceiling.
Exterior of the finished bakery in winter, with loading docks, an exterior stair and the batching silos
The finished plantThe plant in operation, with the outdoor batching silos at right.
Exterior of the long converted industrial building with loading docks during construction
The buildingA converted structure, retrofitted for a new automated bakery.
Panorama of the bakery floor with the concrete slab removed and underground conduit being laid in trenches
The empty floorThe concrete slab removed, ready for trenching.
Rows of grey PVC conduit laid in a trench across the open bakery floor
TrenchingUnderground feeds to the wet areas and production sub-services. With the floor already open, this saved the cost of rooftop conduit.
Rows of underground conduit curving through a trench across an open bakery floor
Around the columnsUnderground conduit routed around the building columns.
Clusters of conduit stub-ups held in timber frames ready for the concrete pour
Stub-upsConduit stubbed up to match future machine locations.
Power cables brought up through conduit stubs in a concrete equipment pad, with cable tray overhead
Equipment padCables brought up through the pad before the cabinets were set.
Incoming cables rising into an MCC section, viewed from below
Incoming cablesFeeders rising into a motor control centre section, ready to land.
Feeder cables landed on the A, B and C bus inside an MCC section
Incoming feedersPhase conductors landed on the A, B and C bus.
Lineup of motor control centre sections with doors open in an electrical room
Motor control centresMCCs in a key section of the plant.
Tall electrical room with motor control centres and control cabinets, conduit running down the white walls
Electrical roomMCCs and control cabinets, with conduit run down from above.
Control cabinets lined up along a tall white wall with vertical conduit runs overhead
Control cabinetsProcess control cabinets along the wall, with power and control run down from overhead.
Electrician landing field wiring on PLC input and output modules inside a large control cabinet
Control wiringTerminations and I/O landed in a process control panel.
Banks of conduit running up a white wall into large control cabinets
Conduit to the cabinetsBanks of rigid conduit dropping into the Zeppelin batching control panels.
Row of new outdoor ingredient silos beside the building
The silosOutdoor silos for the batching system.
Electrician on a boom lift working at the top of a row of outdoor ingredient silos with conduit running down each silo
Silo wiringLevel detection, valves and motors terminated at the top and bottom of each silo.
Four load cell junction boxes wired in conduit on a stainless batching hopper frame
Batching scalesLoad cell junction boxes wired on a batching hopper.
Overhead batching structure with crews working at height above a stainless operator station
Batching structureCrews working at height on the overhead batching structure.
Pumps and motors beneath stainless process tanks, wired through junction boxes and conduit
Process tanksPumps and motors under the process tanks, wired and in conduit.
Tall stainless cooling spirals with access stairs and platforms, and an infeed conveyor in the foreground
Cooling spiralsAll devices and main power feeds wired to the cooling spirals, with I/O checks and start-up support for the OEM.
Plant floor with overhead conveyors installed, process equipment arriving and lifts in use
Production floorThe Rexfab conveyor system for product transfer, with motors wired on aluminum rigid drops from the ceiling.
Process line equipment and conveyors being installed on the production floor, with an electrician in the foreground
Process lineProcess line equipment going in as the plant neared completion.
Exterior of the finished bakery in winter, with loading docks, an exterior stair and the batching silos
The finished plantThe plant in operation, with the outdoor batching silos at right.

On schedule, and right the first time

Engineering approvals took several months longer than planned, and the finish date didn’t move. Careful coordination with the mechanical and other sub-trades kept the schedule on track, and with a large crew on site, potential backlogs were identified early to eliminate wasted labour hours. A point of pride for the team: almost no start-up or device termination issues.

Electrical contracting & control wiringUnderground conduit & stakeoutsHV substation & distribution6000 A & 3000 A LV switchboardsSub load centres & MCCsMain power distribution designZeppelin batching systemRexfab, AFA & AMF OEM installsOEM I/O checks & start-upData, fibre & fire alarmFood-grade lighting & clean designPLC & shift coverage