Contact us
Home/Design-Build & Power/Case Study: 5 MVA Rooftop Power Upgrade
New three-bay 44 kV switchgear lifted by crane against a clear sky
Case studyLife SciencesDesign-BuildCritical PowerIn progress

Adding 5 MVA to a Life Sciences Plant, Up on the Roof

A turnkey design-build capacity upgrade: a new 44 kV service, rooftop switchgear and transformer, and a 5000 A switchboard lowered through the roof. Sheridan is prime contractor and engineer, planned around a plant that can’t stop.

5 MVAAdded capacity
44 kVNew service & 3-bay switchgear
5000 A600 V switchboard & cable bus
RooftopPlatform for switchgear & transformer

The challenge

A life sciences manufacturer needed another 5 MVA at an operating facility, a live and sensitive manufacturing environment where shutdowns have to be kept to a minimum.

The plant’s existing 44 kV switchgear fed transformers it depended on, the new equipment had lead times of up to a year, and the new utility connection needed approvals before anything could be built.

Running plantExisting 44 kV gear in serviceYear-long lead timesUtility & ESA approvals

Engineered and built by Sheridan.

Sheridan took the project turnkey as prime contractor, responsible for the engineering. Instead of replacing the existing switchgear, our design adds a new 44 kV demarcation at the site entrance and puts the new switchgear and a 5 MVA transformer on a rooftop platform above the electrical room. A 5000 A cable bus drops through the roof to a new 5000 A switchboard, and a second feeder from the new switchgear back-feeds the existing 44 kV gear.

The result: the existing switchgear and transformers stay untouched, and the plant needs only short shutdowns to reconfigure the service and transfer the feeder.

Turnkey design-buildSheridan engineeringExisting gear untouchedMinimal shutdowns

How it comes together

From the site entrance to the roof.

Engineering, approvals and long-lead orders first, then the installation in planned phases.

  1. EngineeringFrom award

    Design the new service

    Single lines and rooftop layouts, a grounding study, and a pre-engineering meeting with the owner and the utility. High- and low-voltage design submitted to ESA, and the utility’s Offer to Connect in place before construction.

  2. ProcurementOrdered early

    Order the long-lead gear

    Shop drawings reviewed and orders placed within weeks of award: the 44 kV switchgear at about 54 weeks to build, the 5 MVA transformer at about 50, the 5000 A switchboard at about 32 and the cable bus at about 28.

  3. Site entrancePhase 1

    New 44 kV demarcation

    A new dip pole and 44 kV metering pole at the site entrance, with new 44 kV feeders reusing the existing duct bank.

  4. RoofPhases 2–6

    Open the roof, build the platform

    The roof is cut so the 5000 A switchboard can be hoisted into the second-floor electrical room and anchored, then the roof is remediated. A new rooftop platform is hoisted, set and decked, with grounding and bonding of the metalwork around it.

  5. Rooftop gearPhases 7–8

    Transformer and switchgear up top

    The 5 MVA, 44 kV–600 V liquid-filled transformer and the three-bay 44 kV switchgear are craned onto the platform, and the 5000 A cable bus is completed down to the switchboard.

  6. CutoverPlanned shutdown

    Power on the new service

    In a planned shutdown, the utility makes safe and removes the legacy 44 kV feeder, new feeders are connected to the new switchgear and back to the existing gear, and the building comes back on the new service.

Why the roof

Putting the new switchgear and transformer above the electrical room kept the existing 44 kV switchgear and transformers in service and untouched. Replacing the existing gear was priced too, but it would have cost significantly more and needed far more downtime to rework and reconnect the existing transformers.

On site

Up to the roof. More photos to come.

New switchgear and equipment strapped to a lowboy trailer below the roof, Sheridan trucks parked beyond
Delivery dayNew switchgear and equipment arrive on a lowboy at the base of the building.
Crane lifting a new equipment section off the trailer toward the roof as the crew watches below
Up to the roofEach section craned from the trailer up to the new rooftop platform.
Three-bay 44 kV switchgear on the crane hook, boom overhead
44 kV switchgearThe new three-bay rooftop switchgear on the hook.
Turnkey design-buildSheridan engineering44 kV demarcation & metering3-bay 44 kV switchgear5 MVA rooftop transformer5000 A cable bus5000 A 600 V switchboardRooftop platformGrounding studyESA & utility approvals

Need more capacity?

Send us the load you need to add. We’ll engineer where it goes and how to get there with the least downtime.