Adding 5 MVA to a Life Sciences Plant, Up on the Roof
A turnkey design-build capacity upgrade: a new 44 kV service, rooftop switchgear and transformer, and a 5000 A switchboard lowered through the roof. Sheridan is prime contractor and engineer, planned around a plant that can’t stop.
The challenge
A life sciences manufacturer needed another 5 MVA at an operating facility, a live and sensitive manufacturing environment where shutdowns have to be kept to a minimum.
The plant’s existing 44 kV switchgear fed transformers it depended on, the new equipment had lead times of up to a year, and the new utility connection needed approvals before anything could be built.
Engineered and built by Sheridan.
Sheridan took the project turnkey as prime contractor, responsible for the engineering. Instead of replacing the existing switchgear, our design adds a new 44 kV demarcation at the site entrance and puts the new switchgear and a 5 MVA transformer on a rooftop platform above the electrical room. A 5000 A cable bus drops through the roof to a new 5000 A switchboard, and a second feeder from the new switchgear back-feeds the existing 44 kV gear.
The result: the existing switchgear and transformers stay untouched, and the plant needs only short shutdowns to reconfigure the service and transfer the feeder.
How it comes together
From the site entrance to the roof.
Engineering, approvals and long-lead orders first, then the installation in planned phases.
- EngineeringFrom award
Design the new service
Single lines and rooftop layouts, a grounding study, and a pre-engineering meeting with the owner and the utility. High- and low-voltage design submitted to ESA, and the utility’s Offer to Connect in place before construction.
- ProcurementOrdered early
Order the long-lead gear
Shop drawings reviewed and orders placed within weeks of award: the 44 kV switchgear at about 54 weeks to build, the 5 MVA transformer at about 50, the 5000 A switchboard at about 32 and the cable bus at about 28.
- Site entrancePhase 1
New 44 kV demarcation
A new dip pole and 44 kV metering pole at the site entrance, with new 44 kV feeders reusing the existing duct bank.
- RoofPhases 2–6
Open the roof, build the platform
The roof is cut so the 5000 A switchboard can be hoisted into the second-floor electrical room and anchored, then the roof is remediated. A new rooftop platform is hoisted, set and decked, with grounding and bonding of the metalwork around it.
- Rooftop gearPhases 7–8
Transformer and switchgear up top
The 5 MVA, 44 kV–600 V liquid-filled transformer and the three-bay 44 kV switchgear are craned onto the platform, and the 5000 A cable bus is completed down to the switchboard.
- CutoverPlanned shutdown
Power on the new service
In a planned shutdown, the utility makes safe and removes the legacy 44 kV feeder, new feeders are connected to the new switchgear and back to the existing gear, and the building comes back on the new service.
Why the roof
Putting the new switchgear and transformer above the electrical room kept the existing 44 kV switchgear and transformers in service and untouched. Replacing the existing gear was priced too, but it would have cost significantly more and needed far more downtime to rework and reconnect the existing transformers.
On site
Up to the roof. More photos to come.